We have a task to design an embedded retaining solution for 3 underground floors in an urbain environment . The ground is however sloped at 19 degree angle. As shown in the figure attached, the excavated upper part will be about 40 ft and the length of the excavation is about 118 ft.
Geotechnical investigations are under way but it's fairly certain there is no groundwater table in the region and the soil is mostly hard Marly sands, in this situation of sloping ground what are the possible solution baring in mind at the entrance level only 3-4 ft will be excavated?
We have a task to design an embedded retaining solution for 3 underground floors in an urbain environment . The ground is however sloped at 19 degree angle. As shown in the figure attached, the excavated upper part will be about 40 ft and the length of the excavation is about 118 ft.
Geotechnical investigations are under way but it's fairly certain there is no groundwater table in the region and the soil is mostly hard Marly sands, in this situation of sloping ground what are the possible solution baring in mind at the entrance level only 3-4 ft will be excavated?