FRACH23
Structural
- Aug 21, 2015
- 28
I was designing an end plate moment connection for a SMF Building at SDC D, and having trouble with very large demand moment (3,000 kN-m) due to overstrength. My girder is 800mm deep. I
1. I checked DG and it seems the most i could do was 8 tension bolt connection (2 hor x 4vert each flange, 16 total bolts at joint). Since my column was fairly large and is a built-up section, i was thinking of making more tension bolts, say 16 tension bolts (4 hor x 4 vert each flange, 32 total bolts at joint), but was worried i may have deviated any AISC seismic design rule.
2. I could make a haunch under the girder, but also worried i may deviate the "protect zone rule"
3. My other option into make Bolted Flange Plate (BFP). But at a given overstrength connection force, i may need to provide 4 columns of bolts. Could i do this without deviating any AISC rule (typical detail i see shows only two bolt columns (1 each side of flange)
4. How do we establish the particular location of protect zone for a SMF frame?
Any guidance would be highly appreciated.
1. I checked DG and it seems the most i could do was 8 tension bolt connection (2 hor x 4vert each flange, 16 total bolts at joint). Since my column was fairly large and is a built-up section, i was thinking of making more tension bolts, say 16 tension bolts (4 hor x 4 vert each flange, 32 total bolts at joint), but was worried i may have deviated any AISC seismic design rule.
2. I could make a haunch under the girder, but also worried i may deviate the "protect zone rule"
3. My other option into make Bolted Flange Plate (BFP). But at a given overstrength connection force, i may need to provide 4 columns of bolts. Could i do this without deviating any AISC rule (typical detail i see shows only two bolt columns (1 each side of flange)
4. How do we establish the particular location of protect zone for a SMF frame?
Any guidance would be highly appreciated.