beyond86

Electrical
Sep 24, 2017
146
Hi! Need yours help with ETAP and check synchronization.
I'm trying to make condition when two independent systems unite by closing intertie CB. So I need to set some angel between two systems and then check synchronization with some parameters. How I can to setup angle between voltage in ETAP?
Thanks!
 
Replies continue below

Recommended for you

Can you please confirm what type of study you are running ?
 
Could be wrong...I don't think any study software can do that. Standard sync check relays use +/-10 degrees.

Mike
 