Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Excavation Rate 1

Status
Not open for further replies.

blackford

Civil/Environmental
Feb 17, 2005
4
I need to work out the £ per cubic metre (+10% profit margin) for the following:
EXCAVATOR data:
180 degree output 50cu m/hr
costs including operator = £600 per/day
Lorries: 10 cubic metre capacity. Cost including driver = £300 per/day
SITE data: 5000 cubic metre excavated. Haul distance is 4kl at average speed of 30km/hr. lorry loading time 12 minutes and tipping time 4 minutes. Tipping charge £2 per cubic metre. Bulking factor for material expected to be 25%.
 
Replies continue below

Recommended for you

6250 m^3 625 lorries
125 hrs. 0.53 hr./lorry
15.625 days 331.25 hrs.
£9,375 £24,922

Total £37,727

Cost £6.04 per m^3
 
I would like to say thanks to earthguy for responding.

 
Status
Not open for further replies.

Part and Inventory Search

Sponsor