mbk2k3
Electrical
- Nov 18, 2010
- 97
44kV system (3 phase, 3 wire).
This is an existing substation plant that is in-service and we can't de-energize due to customer uptime requirements.
While doing some excavation work for ductbanks/concrete pads/etc, the civil contractor has run into the existing ground grid (done years ago by others).
We have a drawing of the existing system, but no ground grid study. There are several grids and loops all tied together. Only a small part of the grid is conflicting with our scope of work.
We have a plan to use temporary ground straps and throw in an equivalent number of rods so we can eliminate this small part of the grid that is causing the conflict. But i'm not sure how this is going to effect step/touch/GPR levels and whether its safe to work while its live?
How do others work around this issue?
Is it safe to work on buried ground grid conductors while the 44kV system is live and energized?
This is an existing substation plant that is in-service and we can't de-energize due to customer uptime requirements.
While doing some excavation work for ductbanks/concrete pads/etc, the civil contractor has run into the existing ground grid (done years ago by others).
We have a drawing of the existing system, but no ground grid study. There are several grids and loops all tied together. Only a small part of the grid is conflicting with our scope of work.
We have a plan to use temporary ground straps and throw in an equivalent number of rods so we can eliminate this small part of the grid that is causing the conflict. But i'm not sure how this is going to effect step/touch/GPR levels and whether its safe to work while its live?
How do others work around this issue?
Is it safe to work on buried ground grid conductors while the 44kV system is live and energized?