Hi All,
We have LV power plant our all generators running on sharing mode,now we have a project to import power from grid for this we installed 11/.04kv transformer.
We have to synch. our existing system with grid (forward synchronization) & also we need to synch. grid to our system means (reverse synchronization).
My question is when we synch. to grid so what is the mode of our generators, is they running on sharing mode or power mode (fixed load)????
If we purchase only one panel for both forward & reverse synchronization so what we have to instruct the panel maker for both functions???
Waiting for your valuable comments/suggestions, thanks.
We have LV power plant our all generators running on sharing mode,now we have a project to import power from grid for this we installed 11/.04kv transformer.
We have to synch. our existing system with grid (forward synchronization) & also we need to synch. grid to our system means (reverse synchronization).
My question is when we synch. to grid so what is the mode of our generators, is they running on sharing mode or power mode (fixed load)????
If we purchase only one panel for both forward & reverse synchronization so what we have to instruct the panel maker for both functions???
Waiting for your valuable comments/suggestions, thanks.