Skibur
Structural
- Aug 6, 2019
- 3
I have an existing 6" slab with #5 @ 12" OC. It is unknown whether or no the reinforcing extends through the joints. It was built in the 90's so its possible they used the old detail of extending 50% of the reinforcing through the joints. I am wondering how others are dealing with placing new equipment onto existing slabs. The "Designing Slab on Ground" guide takes into account flexural stresses in the slab where as the tables provided by PCA (i believe this is correct) does not. The results from these methods are VERY different. I have vessels that weigh 40,000 lbs in which i am planning to cut out slab and replace in these areas. Another piece of equipment weight 8000 lbs and has 6 small leveling feet. Another piece of equipment weight about the same, 8000 lbs, however is skid mounted. I also have storage racking (8'x4'x16' tall). The 6" slab is capable of handling these loads ignoring joints. What methods are others using?
1. Housekeeping pad on top of existing pad, ignore the joints.
2. Saw cut existing slab then install housekeeping pad on top of existing pad to match the perimeter of the saw cut
3. Ignore the joints and accept the flexural cracking that may occur and sit directly on the existing slab
As for the racking, I have not calculated loading, however, the feet are directly on or withing 12" of the control joints.
Any help or guidance would be appreciated. I did come across a document that someone posted ARMY TM 5-809, Concrete Floor Slabs on Grade Subjected to Heavy Loads, but is a very old document, 1987.
Thank you in advance
1. Housekeeping pad on top of existing pad, ignore the joints.
2. Saw cut existing slab then install housekeeping pad on top of existing pad to match the perimeter of the saw cut
3. Ignore the joints and accept the flexural cracking that may occur and sit directly on the existing slab
As for the racking, I have not calculated loading, however, the feet are directly on or withing 12" of the control joints.
Any help or guidance would be appreciated. I did come across a document that someone posted ARMY TM 5-809, Concrete Floor Slabs on Grade Subjected to Heavy Loads, but is a very old document, 1987.
Thank you in advance