Hi,
I have an existing steel beam which currently sits on a column
I would like to demolish column and let beam into a new LVL beam.
Can I use two angles:
1. Field bolted to either side of web of existing beam and
2. Lag screwed / bolted through face of new LVL
We want avoid any filed welding due to combustibility...
Any comments or suggestions?
Thanks
I have an existing steel beam which currently sits on a column
I would like to demolish column and let beam into a new LVL beam.
Can I use two angles:
1. Field bolted to either side of web of existing beam and
2. Lag screwed / bolted through face of new LVL
We want avoid any filed welding due to combustibility...
Any comments or suggestions?
Thanks