What is reasonable settlement for a 25 ton pile? Has other engineers designed buildings for an expected settlement in excess of 2"? Did differential settlement occur after construction?
Say a proposed 4 story building (with full garage), is estimated to settle 2.3 inches over 30 years. Column loads are 225 kips. Pile caps consist of 5 piles. Is this amount of settlement too high? Would you ask the geotech to analyze a different type of pile?
Thanks,
Mark
Say a proposed 4 story building (with full garage), is estimated to settle 2.3 inches over 30 years. Column loads are 225 kips. Pile caps consist of 5 piles. Is this amount of settlement too high? Would you ask the geotech to analyze a different type of pile?