nilaypathak
Civil/Environmental
- Sep 5, 2010
- 66
I am working on Process PreEngineerd Metal building. I came across explosion vent requirements from Code compliance reports and ELM(Engineer loss Management) reports.
There are certain level of measure to void event of explosion. By this argument we submitted variance to safety officer.
He replied that provide assurance in you argument that there will not changes of explosion by this measures. Virtually it is not possible to state in the latter.
I would like to have input/help/suggestion on below items:
1)Looking for reference material which would provide me more detail to plug in explosion vent variance application to safety officer.
2) In case of disapproval variance, provide me agencies name would help me to decide upon locations and size of the vents on the building walls
Thanks you in advance.
There are certain level of measure to void event of explosion. By this argument we submitted variance to safety officer.
He replied that provide assurance in you argument that there will not changes of explosion by this measures. Virtually it is not possible to state in the latter.
I would like to have input/help/suggestion on below items:
1)Looking for reference material which would provide me more detail to plug in explosion vent variance application to safety officer.
2) In case of disapproval variance, provide me agencies name would help me to decide upon locations and size of the vents on the building walls
Thanks you in advance.