ASHB
Civil/Environmental
- Aug 23, 2024
- 1
Hi,
There was an existing boundary wall of height 1.5m above the footing. The ground level on one side of the existing boundary wall needed to be lowered. Thus, during excavation the footing of the boundary wall was exposed. Any method on how to protect this footing. Will mass concrete only be sufficient to prevent any overturning moment if any.
Thanks
There was an existing boundary wall of height 1.5m above the footing. The ground level on one side of the existing boundary wall needed to be lowered. Thus, during excavation the footing of the boundary wall was exposed. Any method on how to protect this footing. Will mass concrete only be sufficient to prevent any overturning moment if any.
Thanks