My experience says that the buried pipe should be modelled till virtual anchor lenght in a software... some times we model twice of the virtual anchor length. Virtual anchor length can be calculatd by hand calculations.
However client is asking us to model 10 km long pipeline in CAESAR II. When we put forward the above statement and denied modelling the entire run client asked us to give reference document where it is stated that beyond virtual ancor line need not be modelled and generic calculations for equivalnt stress are acceptable. Further how to ensure the safety of cold bends?
any inputs
However client is asking us to model 10 km long pipeline in CAESAR II. When we put forward the above statement and denied modelling the entire run client asked us to give reference document where it is stated that beyond virtual ancor line need not be modelled and generic calculations for equivalnt stress are acceptable. Further how to ensure the safety of cold bends?
any inputs