sjohns4
Civil/Environmental
- Sep 14, 2006
- 123
I'm preparing a PER for a training facility that sees incredibly variable flows. The variation will happen weekly. There can be intermittent periods of extremely high flows (~140,000 GPD) flowed by periods of extremely low flows (~8,000 GPD), and various levels between. I'm using 350 mg/l BOD & TSS at the moment as the collection system is minimal and will be brand new. Actual water use and raw flow testing from a similar facility are in the process - regardless of actual flow and loadings, the same variability and flow swings will be there so I think the challenge will be similar.
We only need to meet a 30/30 effluent, no N or P limits, but we do have a turbidity limit of <2 NTU when using conventional treatment and filtration and a turbidity limit of <0.2 NTU when using an MBR.
In my mind, the flow is the easy part. I think the obvious solution would be multiple process trains. I'm not real confident on the bugs, solids, and overall process efficiency.
My first round of calcs on paper show I can use 2 trains and maintain parameters between operating the secondary process as a complete mix activated sludge plant during peak flows and an extended aeration type plant during low flows.
Complete Mix / Peak Flows:
2 basins in operation
Hydraulic Detention Time: 5.5 Hrs
MLSS: 4000 mg/L (1,086 pounds in basins)
Basin Loading: 95.25 # BOD/d/1000 cf
F:M - 0.51
SRT: 5.85 Days
Extended Aeration / Low Flows:
1 basin in operation
Hydraulic Detention Time: 48.8 Hrs (Long for EA...is that really a problem if we keep the DO right?)
MLSS: 5000 mg/L
Basin Loading: 10.74 # BOD/d/1000 cf
F:M - 0.05
SRT: 22.62 Days
Ramping down sounds simple enough: transfer mixed liquor from one plant to the next and waste sludge.
When everyone shows back up I'm showing aeration basin solids should be re-established in a about a day with no sludge wasting.
Assuming all of the above are correct and doable, how will the process react to the changes?
Thanks for any wisdom that can be provided.
Mike
We only need to meet a 30/30 effluent, no N or P limits, but we do have a turbidity limit of <2 NTU when using conventional treatment and filtration and a turbidity limit of <0.2 NTU when using an MBR.
In my mind, the flow is the easy part. I think the obvious solution would be multiple process trains. I'm not real confident on the bugs, solids, and overall process efficiency.
My first round of calcs on paper show I can use 2 trains and maintain parameters between operating the secondary process as a complete mix activated sludge plant during peak flows and an extended aeration type plant during low flows.
Complete Mix / Peak Flows:
2 basins in operation
Hydraulic Detention Time: 5.5 Hrs
MLSS: 4000 mg/L (1,086 pounds in basins)
Basin Loading: 95.25 # BOD/d/1000 cf
F:M - 0.51
SRT: 5.85 Days
Extended Aeration / Low Flows:
1 basin in operation
Hydraulic Detention Time: 48.8 Hrs (Long for EA...is that really a problem if we keep the DO right?)
MLSS: 5000 mg/L
Basin Loading: 10.74 # BOD/d/1000 cf
F:M - 0.05
SRT: 22.62 Days
Ramping down sounds simple enough: transfer mixed liquor from one plant to the next and waste sludge.
When everyone shows back up I'm showing aeration basin solids should be re-established in a about a day with no sludge wasting.
Assuming all of the above are correct and doable, how will the process react to the changes?
Thanks for any wisdom that can be provided.
Mike