rockman7892
Electrical
- Apr 7, 2008
- 1,171
We are getting ready to conduct earth resistance testing in our plant using the fall of potential method. We will most likely contract this work out to a certified testing company.
In all of the research that I've done regarding this procedure it seems that in order to complete this test accurately the ground grid under test must be isolated from any equipment and other ground grids. In our plant we have several of these ground grids surrounding our various electrical rooms containning our 4160/480V unit substations. All of these ground grids are tied together througout the plant as well as tied back to the ground grid installed at the utility transformer.
My question and possbile obstactle to having this testing completed sucessfully is weather or not we must isolate each of these ground grids for testing, or do we treat the whole plant grounding system as one grid? If we treat the plant as one grid then we will need to go out a very far distance with our test rod.
Half of plant is now in service. I know that it is a must to have the systems under test de-energized for these test and I need to plan for this accordingly. I cannot seem to determine however if it is a must to isolate the various ground grids around the electrical rooms as well as isolate the grid from equipment.