Hi,
I was wondering if anyone could help me out with a FT analysis that I am currently conducting.
My question is that in the tree if I have the basic events Failure Rates(#failure/10^6 hrs) instead of the Failure probability and that is the only information I have from my component(basic event) how does the calculations work out? How can I calculate the Failure Rate of the Top event? I have check many text books about FTAs and they all talk about probability calculations, I completely understand the calculations behind the FTA when you have probabilities but the story is different if you have FRs.
I am not sure how the results of the AND gates work out. with OR gates it is easy, a good estimate of the next level event is just the addition of FRs from basic events but for AND gate I am not sure what I need to do.
Is there any suggestions, my fault trees are not complicated at all and I don't have access to any software to do the calculations for me so I am just using Excel.
Any help is greatly appreciated
Mohammad
I was wondering if anyone could help me out with a FT analysis that I am currently conducting.
My question is that in the tree if I have the basic events Failure Rates(#failure/10^6 hrs) instead of the Failure probability and that is the only information I have from my component(basic event) how does the calculations work out? How can I calculate the Failure Rate of the Top event? I have check many text books about FTAs and they all talk about probability calculations, I completely understand the calculations behind the FTA when you have probabilities but the story is different if you have FRs.
I am not sure how the results of the AND gates work out. with OR gates it is easy, a good estimate of the next level event is just the addition of FRs from basic events but for AND gate I am not sure what I need to do.
Is there any suggestions, my fault trees are not complicated at all and I don't have access to any software to do the calculations for me so I am just using Excel.
Any help is greatly appreciated
Mohammad