DaveChowmein
Civil/Environmental
- Jan 20, 2014
- 1
Hi,
I am working on a contract as the Engineer for a project under the FIDIC Red Book 1999.
The Contractor has submitted a quote for a provisional sum which uses an exchange rate different to that in the Contract. Is that possible, or can should it be the exchange rate defined in the contract?
Thanks
I am working on a contract as the Engineer for a project under the FIDIC Red Book 1999.
The Contractor has submitted a quote for a provisional sum which uses an exchange rate different to that in the Contract. Is that possible, or can should it be the exchange rate defined in the contract?
Thanks