broekie
Structural
- Feb 17, 2004
- 150
I am working on a pump station project where the pumps are being replaced and as a result there are some minor structural modifications being done.
One of the modifications that we are doing is "filling in" an existing 16" diamter hole in a 12" thick concrete wall. There used to be an outlet pipe going through this opening, but the pipe is no longer required so the owner would like to fill in the hole.
Any suggestions out there as to the best way to do this? I would like to drill and epoxy some bars into the existing concrete so I was thinking I would actually have the contractor chip out a little more concrete to make that job a little easier.
I have no idea how the contractor would get concrete to fill in this hole, though. The way I see it is that he has to form up both sides of the opening, since this is a vertical wall. But then since the hole is in the middle of the wall, how does he get the concrete to fill in the hole? Can non-shrink grout be used?
Any help would be appreciated. I don't have a lot of experience with stuff like this in the field. Thanks.
One of the modifications that we are doing is "filling in" an existing 16" diamter hole in a 12" thick concrete wall. There used to be an outlet pipe going through this opening, but the pipe is no longer required so the owner would like to fill in the hole.
Any suggestions out there as to the best way to do this? I would like to drill and epoxy some bars into the existing concrete so I was thinking I would actually have the contractor chip out a little more concrete to make that job a little easier.
I have no idea how the contractor would get concrete to fill in this hole, though. The way I see it is that he has to form up both sides of the opening, since this is a vertical wall. But then since the hole is in the middle of the wall, how does he get the concrete to fill in the hole? Can non-shrink grout be used?
Any help would be appreciated. I don't have a lot of experience with stuff like this in the field. Thanks.