LHiggins
Structural
- Apr 23, 2007
- 12
I'm designing a 180' flag pole with a 40’x80’ flag. I used NAAMM's FP1001-07 but updated loads using ASCE 7-10. My question has to do with the footing and embedding the pole. The pole base is a 42" diameter steel pipe sitting in a 52" corrugated sleeve. The manufacturer/installer insists that the sleeve be filled with sand and that no grout is necessary. The footing itself is 6’ diameter and 19’ deep concrete. I’ve agreed to the sand but am insisting on 6” of non-shrink grout at the top so that the pipe has something to bear on and transfer the force to the footing at the top. Is there either a specification or standard somewhere that would shed some light on the grout/sand installation?