- Jul 7, 2006
- 152
Dear all,
In our refinery we have some PSV designed to discharge to atmosphere, most of them are on top of ADU, FCCU and visbreaking main fractionators. Because we consider that as safety and environmental issue we want to connect them to flare. This is problem because when we calculated effluent quantities we got result that we need to build new flare.
Is there any ideas how to connect this PSV to flare and avoid building new flare?
Regards,
Milutin