mcmg
Chemical
- Feb 3, 2016
- 4
Hi all,
We have two flare system, hot and cold. The flare tips are stacked side by side, approximately ~0.4 to 0.5m difference, center to center. The plan is to turn off the hot flare as the hot KO drum is intended to be inspected. The cold flare is still, however, in service as we have some equipment connected to it that are in service. The hot flare still have some PSV's connected, but mostly fire case PSVs, and the actions to be taken for this is to stop any hot work activity on the equipment connected.
I am unsure if there are any safety implications if we proceed with this path forward, i.e, as there may be burned HCs and steam, is there a potential for the fluids release to "go" into the adjacent stack, given that there wind dynamics and release velocity (depending on the instances of the HC's flared) may change. We've tried to ask the vendor and there was no definite answer.
Thank you all.
We have two flare system, hot and cold. The flare tips are stacked side by side, approximately ~0.4 to 0.5m difference, center to center. The plan is to turn off the hot flare as the hot KO drum is intended to be inspected. The cold flare is still, however, in service as we have some equipment connected to it that are in service. The hot flare still have some PSV's connected, but mostly fire case PSVs, and the actions to be taken for this is to stop any hot work activity on the equipment connected.
I am unsure if there are any safety implications if we proceed with this path forward, i.e, as there may be burned HCs and steam, is there a potential for the fluids release to "go" into the adjacent stack, given that there wind dynamics and release velocity (depending on the instances of the HC's flared) may change. We've tried to ask the vendor and there was no definite answer.
Thank you all.