Guest
I have a problem which occured on site. There is post tensioned flat plate which is broken up into 2 pours. Props supporting the slab in Pour 1 were removed along the column line separating the 2 pours after the slab had been fully stressed. The problem is that there is one column which does not line up with the rest of the columns and this column is actually locating in Pour 2. This means that for that particular span, the slab is hanging without support until the second pour is finished and the tendons are coupled together. The props in that area should have been left in place until the adjacent pour has been poured and the whole length of tendons in those spans fully stressed.
Here are the problems.
After the props had been removed, the slab exhibited excessive amount of deflection (approx 50mm-60mm) for a 8m span slab. Some cracks were also observed underneath. The props were then put back underneath that zone in the effort to reduce the deflection.
My question is:
Is it possible to use a hydraulic jack to push the slab back up without damaging the slab itself? (to reduce the visual impact and also to couple the tendons in Pour 2)
Would the deflection be reduced after the tendons are coupled to the one in the second pour?
I would also welcome other suggestions.
Thanks
Here are the problems.
After the props had been removed, the slab exhibited excessive amount of deflection (approx 50mm-60mm) for a 8m span slab. Some cracks were also observed underneath. The props were then put back underneath that zone in the effort to reduce the deflection.
My question is:
Is it possible to use a hydraulic jack to push the slab back up without damaging the slab itself? (to reduce the visual impact and also to couple the tendons in Pour 2)
Would the deflection be reduced after the tendons are coupled to the one in the second pour?
I would also welcome other suggestions.
Thanks