TaviB
Geotechnical
- Jun 9, 2017
- 9
Hello guys,
I have a question. Some relatives want to buy a new flat.
- non-seismic zone (ag = 0,08 g)
- build with load bearing walls on contour and with a column in middle (30cmx30cm)------> structural system is a flat slab with perimeter beams
- slab is 15 cm thick, and the reinforcement plan of the slab is attached.
- Ved: punching shear force - 170 kN
There is a problem from my point of view, there is a pipe, which was put after the building was finished, and an opening was made just near the column. From my point of view, the punching shear capacity dropped with about 20% because of this.
There are some stirrups placed (see plan in right) over there, but when the opening was done, we could not see more then 1, so i do not think there are all of them (52). Maybe there are 25.
Do you think it should be considered a consolidation of the column? I ask this because i know that shear punch failure is quite a big problem. Or because of the small size of the opening no problems can occur?
Is the thickness of 15 cm a enough for a flat slab in this case?
Is the place of opening a good one in this case? I mean it is better to be there instead left of the column? Where the is a bigger span?
Thank you!
I have a question. Some relatives want to buy a new flat.
- non-seismic zone (ag = 0,08 g)
- build with load bearing walls on contour and with a column in middle (30cmx30cm)------> structural system is a flat slab with perimeter beams
- slab is 15 cm thick, and the reinforcement plan of the slab is attached.
- Ved: punching shear force - 170 kN
There is a problem from my point of view, there is a pipe, which was put after the building was finished, and an opening was made just near the column. From my point of view, the punching shear capacity dropped with about 20% because of this.
There are some stirrups placed (see plan in right) over there, but when the opening was done, we could not see more then 1, so i do not think there are all of them (52). Maybe there are 25.
Do you think it should be considered a consolidation of the column? I ask this because i know that shear punch failure is quite a big problem. Or because of the small size of the opening no problems can occur?
Is the thickness of 15 cm a enough for a flat slab in this case?
Is the place of opening a good one in this case? I mean it is better to be there instead left of the column? Where the is a bigger span?
Thank you!