HVAC-Novice
Mechanical
- Jul 29, 2022
- 321
I have a project with a suspended make-up air unit. The gas connection is steel-piped. The manufacturer doesn't show flex connection, but they also cover curb-mounted etc.
A mechanic pointed out the unit will vibrate and may sway a bit and requested there to be a flex connection. Is this typical and should be done for all units? The previous unit didn't have flex connection, but that doesn't mean it isn't needed.
I also want to know what to detail and specify in the future.
our code is IFGC.
A mechanic pointed out the unit will vibrate and may sway a bit and requested there to be a flex connection. Is this typical and should be done for all units? The previous unit didn't have flex connection, but that doesn't mean it isn't needed.
I also want to know what to detail and specify in the future.
our code is IFGC.