I have a client who has another building on campus where the interior slab on grade detail was totally floating and there is significant amount of floor finish cracking around the perimeter.
They really want me to tie the simple 4" slab on grade into the fdn wall. There is 8" masonry above the 14" concrete foundation wall. Has anybody ever toothed the slab into the masonry to hold it in place? I'm inclined to think the problem slab was subjected to warping/curling due to poor detailing/curing etc....during the first construction. What do you guys think?
They really want me to tie the simple 4" slab on grade into the fdn wall. There is 8" masonry above the 14" concrete foundation wall. Has anybody ever toothed the slab into the masonry to hold it in place? I'm inclined to think the problem slab was subjected to warping/curling due to poor detailing/curing etc....during the first construction. What do you guys think?