jaymiess
Structural
- May 20, 2005
- 10
Working on a case where transformer pit flooded and water entered underground conduit and entered homeowners basement where electrical service enters the house. Caused major flooding damage because house was downhill from transformer. Beginning of conduit in transformer pit was resting on the ground and wide open (unsealed). Question is, is there anything in NEC or other code or standard procedure requiring opening of conduit to be above surface of bottom of transformer pit to prevent water from entering it when pit gets flooded? Thanks so much in advance for any help on this.