I have been obsessed over a structural question to which I cannot find any clear answer. When calculating a built-up floor beams with the code tables in part 9, there are tables for beams supporting no more than 1, 2 or 3 floors. Does that mean that I simply count the number of floors over that beam? That's what I always did but a few colleagues have been arguing that you only use the tables for 2 or 3 floors if there is supporting walls over that beam and not other floors supported by other beams. Is there any source of information that specifically explain the answer?