struct_eeyore
Structural
- Feb 21, 2017
- 264
I'm looking for disambiguation of Section 110.8.3 in the FBC.
The section says "The fee owner of a threshold building shall select and pay all costs of employing a special inspector"
Is this to be interpreted that the owner of the building must be the contracting party, or can the GC hire one with owners approval?
Thanks in advance!
The section says "The fee owner of a threshold building shall select and pay all costs of employing a special inspector"
Is this to be interpreted that the owner of the building must be the contracting party, or can the GC hire one with owners approval?
Thanks in advance!