AZEEMM1
Electrical
- May 19, 2004
- 5
I'm new here and my background is Electrical so excuse the simplicity of the approach.
I'm doing some project work in the US and have the folllowing question (all measuers are US):
I have a 50,000 gallon Water Tank that overflows in the event of a main pump failure (catastrophic-happened twice already). Flow IN is 60,000Gal/Min, cannot be stopped or slowed down otherwise we damage equipment.
I want to notch the top of the well and have it spill over into a concrete spillway and redirect the flow away frmo the buildings. The questions is how big do I make the 'hole' at the neck of the well. I only have access to one side, so I can equate an answer in square metres (feet over here!) accordingly.
Thanks in advance.
A
I'm doing some project work in the US and have the folllowing question (all measuers are US):
I have a 50,000 gallon Water Tank that overflows in the event of a main pump failure (catastrophic-happened twice already). Flow IN is 60,000Gal/Min, cannot be stopped or slowed down otherwise we damage equipment.
I want to notch the top of the well and have it spill over into a concrete spillway and redirect the flow away frmo the buildings. The questions is how big do I make the 'hole' at the neck of the well. I only have access to one side, so I can equate an answer in square metres (feet over here!) accordingly.
Thanks in advance.
A