FOG Receiving Station

Status
Not open for further replies.

heyerc

Civil/Environmental
Jul 3, 2013
4
We are wanting to begin feeding our digester FOG that is normally transported to a landfill, etc. Our Vac-con truck has to dump it's contents rather than implement a reverse flow. That being said, I need an open top, sloped bottom tank that has a capacity of 20 cubic yards. A pump will need to be installed at the bottom of the tank in order to move the FOG and debris to the headworks. I'm having difficulty finding such a design. Any ideas or links you know of?
 
Replies continue below

Recommended for you

Huber has many designs of this type.
 