RacingAZ
Structural
- Apr 8, 2009
- 189
I have this project where we are putting in a new folding partition at an existing 2nd floor (steel joists, steel deck & concrete). The folding partition mfr. stated that they don't need input from structural as their system is specifically designed for that reason.
It is a system where they have their own proprietary truss beam at the top (with diagonal bracings) to support the partition then a post at each end to simply bear at the elevated floor. I was told that they would provide all the attachments above and below the existing floor. I also been told not to worry about the post reaction to the floor slab (no need to reinforce the existing slab) as their system is rated for a max. of 4000 lbs. at each post for a 3 1/2" thk. min. slab.
I'm very skeptical and find this claim hard to believe so I asked for supporting calcs. I was told that providing engineering for this specific request would cost an additional charge per the signed contract.
So I did some quick calcs based off the allowable capacity of the deck slab and it would take at least an 8’ wide strip of slab to safely spread out the post reaction. Then there is punching shear and the issue with the joists taking that additional load. The weight of the partition has to go somewhere.
I don't think that is reasonable. Anyone here dealt with this type of partition system?
It is a system where they have their own proprietary truss beam at the top (with diagonal bracings) to support the partition then a post at each end to simply bear at the elevated floor. I was told that they would provide all the attachments above and below the existing floor. I also been told not to worry about the post reaction to the floor slab (no need to reinforce the existing slab) as their system is rated for a max. of 4000 lbs. at each post for a 3 1/2" thk. min. slab.
I'm very skeptical and find this claim hard to believe so I asked for supporting calcs. I was told that providing engineering for this specific request would cost an additional charge per the signed contract.
So I did some quick calcs based off the allowable capacity of the deck slab and it would take at least an 8’ wide strip of slab to safely spread out the post reaction. Then there is punching shear and the issue with the joists taking that additional load. The weight of the partition has to go somewhere.
I don't think that is reasonable. Anyone here dealt with this type of partition system?