skimboard20
Structural
- Mar 10, 2021
- 21
I am working on a very simple structure for a generator enclosure. It consists of a couple retaining walls that retain 3 ft max, with a slab-on-grade to support a back-up generator for the client's house. The proposed location of the generator pad is very close to the property line, so we've designed a few soldier piles for the contractor to install temporary shoring. Of course, the contractor would rather not install the soldier piles, so we are currently looking at ways to reduce the excavation cut so that the excavation stays away from the property line.
Currently, the bottom of the footing for the retaining wall is 16" below the slab-on-grade. This is standard for the frost depth in our area. The contractor would like to pour the slab directly on top of the footing (t.o. footing = b.o. slab) or even at the same height as the footing (t.o. footing = t.o. slab), which would reduce their excavation by about 7 inches. At a 1:1 cut, they've now saved 7 inches of horizontal cut as well (we're really reaching here).
The only rebuttal I have is that the bottom of the footing needs to be below the frost depth, measured from the top of the grade. But I'm wondering if this is only for heated structures? Does this still apply to a couple concrete walls that just sit outside and enclose a generator? I haven't been able to find any code language that allows you to not place the footing below the frost depth. What's the worst that would happen if the footing is not below frost depth? Their generator slab cracks a bit?
This has become long-winded, but the short of it is I'm trying to figure out how to respond to this contractor. Can we specify the bottom of the footing above the frost depth?
Any insight here would be appreciated.
Thanks!
Currently, the bottom of the footing for the retaining wall is 16" below the slab-on-grade. This is standard for the frost depth in our area. The contractor would like to pour the slab directly on top of the footing (t.o. footing = b.o. slab) or even at the same height as the footing (t.o. footing = t.o. slab), which would reduce their excavation by about 7 inches. At a 1:1 cut, they've now saved 7 inches of horizontal cut as well (we're really reaching here).
The only rebuttal I have is that the bottom of the footing needs to be below the frost depth, measured from the top of the grade. But I'm wondering if this is only for heated structures? Does this still apply to a couple concrete walls that just sit outside and enclose a generator? I haven't been able to find any code language that allows you to not place the footing below the frost depth. What's the worst that would happen if the footing is not below frost depth? Their generator slab cracks a bit?
This has become long-winded, but the short of it is I'm trying to figure out how to respond to this contractor. Can we specify the bottom of the footing above the frost depth?
Any insight here would be appreciated.
Thanks!