The only time I typically specify (2) rebar matts for footings is when I'm dealing with pre-fab metal buildings with high uplift.
In this conventional building of joist and girders, I'm not anticipating uplift to be as much a requirement, if at all.
My 2-way punching shear forces me to go with 18" thick footing.
At what footing thickness might it be necessary to add a 2nd matt? And why?