Hi,
In a two-way ribbed slab with embedded beams, this table from ACI code for formwork removal says 14 days for slabs and 21 days for beams,
Does that mean the contractor should not remove the formwork of the beams until the 21 days have passed, or are the beams part of the slab and their formwork can be removed with the slab at 14 days?
Thanks!