bbartlet
Structural
- Dec 20, 2007
- 25
I’ve read previous posts about limitations on concrete pour lengths in concrete tanks, but I haven’t found anything regarding standard foundations. I have a project under construction using concrete trench footings and standard wall footings. We require construction joints at a maximum spacing of 60’. This has been part of our standard structural notes and we’ve never had a problem with it before but the contractor says that this limitation throws off their schedule (even though it should've been in his bid) and asked if we could lose this limitation. We told them that we couldn't and that they should leave between 5’ and 60’ between adjacent pours and wait 7 days between the infill pour and to limit the shrinkage effects.
I just wanted to know if we’re being too strict on these limitations and what, if any, others use for the limitations on pour lengths.
I just wanted to know if we’re being too strict on these limitations and what, if any, others use for the limitations on pour lengths.