lcruzz01
Geotechnical
- Oct 26, 2012
- 12
There is project were the design foundation depth was 2 m (6.5 ft). During excavation we found 7 m (23 ft) of non-controlled fill and we suppose it has at least 15 m (50 ft). One of the options was to pour concrete with crushed rock in the first 3 ft followed by an engineered fill till we get to the original foundation depth. I suggested increasing the footing dimensions (initially 26x19 ft) to distribute the load and minimize settlements. I believe the first option can cause settlements due to the excessive depth of fill. What do you guys suggest? We can't use piles because of time delays.