hssbrian
Structural
- Aug 24, 2015
- 10
Hello everyone,
Im designing a simple free standing 14cm cmu 3m tall wall, I need to bounce some ideas with anyone that has an insight or opinion on this matter. This wall will serve as an enclosure for an existing slab on grade due to several reasons we were asked not to modify the slab on grade and just add the enclosure around it. Although I understand that there are several ways to solve one problem and several things, to consider like cost and construction time, I would like to focus on design.. I have attached the existing conditions with two options.
Existing condition: You will be able to see two different details for grade beams at the ends of the slab, this is because they were built in different times.
Option 1: Using isolated footings at 3m o.c. with columns and a bottom beam that will carry the load of the wall
Option 2: Using a strip L shaped footing to not mess with existing
I have made an effort to provide as much information as I can think of, but if you think something else would be relevant please just ask....
Maximum out-of plane load is 0.3kPa (includes seismic)
What do you guys think of option 1? I feel a bit hesistant to dig up below the grade beam but Ill admit is such a small span that realistically it might not be as influencial.
What do you guys think of option 2? I feel a bit hesistant do to it relying mostly on the toe of the footing, although I know this is typical in certain places, I would feel better having a heel restraining out of plane loads
Do you have any suggestions? any typical design? details? or checks you might think I made need to do?
all rebars shown are 12mm
note: i also added a sample of option 2
Thank you in advance....
Im designing a simple free standing 14cm cmu 3m tall wall, I need to bounce some ideas with anyone that has an insight or opinion on this matter. This wall will serve as an enclosure for an existing slab on grade due to several reasons we were asked not to modify the slab on grade and just add the enclosure around it. Although I understand that there are several ways to solve one problem and several things, to consider like cost and construction time, I would like to focus on design.. I have attached the existing conditions with two options.
Existing condition: You will be able to see two different details for grade beams at the ends of the slab, this is because they were built in different times.
Option 1: Using isolated footings at 3m o.c. with columns and a bottom beam that will carry the load of the wall
Option 2: Using a strip L shaped footing to not mess with existing
I have made an effort to provide as much information as I can think of, but if you think something else would be relevant please just ask....
Maximum out-of plane load is 0.3kPa (includes seismic)
What do you guys think of option 1? I feel a bit hesistant to dig up below the grade beam but Ill admit is such a small span that realistically it might not be as influencial.
What do you guys think of option 2? I feel a bit hesistant do to it relying mostly on the toe of the footing, although I know this is typical in certain places, I would feel better having a heel restraining out of plane loads
Do you have any suggestions? any typical design? details? or checks you might think I made need to do?
all rebars shown are 12mm
note: i also added a sample of option 2
Thank you in advance....