bvass
Structural
- May 29, 2014
- 13
Hi All,
I have a simple question that I'd like to get some opinions on. My firm is designing some heavy moment connections for industrial pipe racks that use end plates bolted to column flanges. The connection from the end plate to beam is typically a 5/16" max fillet weld. We have some locations where larger than 5/16" welds are required and start getting into multi-pass sizes. My supervisor is of the opinion that full-pen welds are more cost effective than a multi-pass (say 3/8" max 3-pass) welds. I just wanted to get some general opinions on this matter because to me that does not seem like a cost effective solution. Full-pen requires grinding and special inspection, a multi-pass welds required more weld metal but no inspection or grinding. Intuitively I would think a multi-pass filet would be the way to go but I could be wrong. Opinions?
Thanks,
Brad
I have a simple question that I'd like to get some opinions on. My firm is designing some heavy moment connections for industrial pipe racks that use end plates bolted to column flanges. The connection from the end plate to beam is typically a 5/16" max fillet weld. We have some locations where larger than 5/16" welds are required and start getting into multi-pass sizes. My supervisor is of the opinion that full-pen welds are more cost effective than a multi-pass (say 3/8" max 3-pass) welds. I just wanted to get some general opinions on this matter because to me that does not seem like a cost effective solution. Full-pen requires grinding and special inspection, a multi-pass welds required more weld metal but no inspection or grinding. Intuitively I would think a multi-pass filet would be the way to go but I could be wrong. Opinions?
Thanks,
Brad