Hi Guys,
I wanted to know if it is indicated any guidelines in ASME boiler and PV codes regarding the use of full vacuum or half vacuum for the design of a PV or a HX, as a general thumb of rule normally, we specify external full vacuum for the steam out condition, so when would considering half vacuum be more realistic and save costs? please guide
I wanted to know if it is indicated any guidelines in ASME boiler and PV codes regarding the use of full vacuum or half vacuum for the design of a PV or a HX, as a general thumb of rule normally, we specify external full vacuum for the steam out condition, so when would considering half vacuum be more realistic and save costs? please guide