SilverArc
Electrical
- Sep 20, 2006
- 82
Hi Everybody..
I have to size a generator for a mine hoist. The mine hoist is 600 HP that means 600 * 746= 447600 W= 447 .6 KW
For some moments of time, the load even becomes 847 HP during acceleration period of the hoist. But this period is in msecs.
The calculations involved come with a -200 HP power fed back to the motor during hoist going down the shaft.
Now what I understood that, if I size a emergency generator for this application, It should be capable of acting as a sink of -200 HP power which means:
200 * 746= 149 KW now I have to convert this in to KVAR.
The motor is fed with a VFD, some of you who have mine hoist experience can comment on this; Power factor with VFD assumed: .8(Please advise, if this PF is not real when it comes to hoisting application)
149 KW= 186 KVA=1111.75 KVAR
Could you advise me, normally to what percent of its size a generator can act as a sink and source of VARS ?
I heard that to sort out this regenerative power issue with mine hoists: Load banks are used. COuld you advise me, where I can find some information about this.
I have given a best shot of my engineering judgement... An advise from some of you who are experts in this area might give me a better direction.
Thanks
I have to size a generator for a mine hoist. The mine hoist is 600 HP that means 600 * 746= 447600 W= 447 .6 KW
For some moments of time, the load even becomes 847 HP during acceleration period of the hoist. But this period is in msecs.
The calculations involved come with a -200 HP power fed back to the motor during hoist going down the shaft.
Now what I understood that, if I size a emergency generator for this application, It should be capable of acting as a sink of -200 HP power which means:
200 * 746= 149 KW now I have to convert this in to KVAR.
The motor is fed with a VFD, some of you who have mine hoist experience can comment on this; Power factor with VFD assumed: .8(Please advise, if this PF is not real when it comes to hoisting application)
149 KW= 186 KVA=1111.75 KVAR
Could you advise me, normally to what percent of its size a generator can act as a sink and source of VARS ?
I heard that to sort out this regenerative power issue with mine hoists: Load banks are used. COuld you advise me, where I can find some information about this.
I have given a best shot of my engineering judgement... An advise from some of you who are experts in this area might give me a better direction.
Thanks