-
1
- #1
JAE
Structural
- Jun 27, 2000
- 15,567
There has been some discussion of this topic in the past, but a recent project investigation has prompted me to post this to see what others think.
Scenario:
A typical, small building (about 6000 sf) one story, wood framed with brick veneer on concrete spread footings.
An A/E firm hires the geotech via the owner and gets a typical geotechnical report, outlining the soil conditions, bearing pressures, stuff about pavements, etc. Nothing real extraordinary except that the geotech warns about a couple of things:
a) Might be some concerns over the bearing soils - and gives certain recommendations about dealing with those concerns.
b) Says that they (the geotech) should review the plans for conformance with their recommendations.
c) Says that they should be hired to do on-site consulting to verify if the soils are ok, that construction practices are proper, to do testing of compaction, etc.
d) Says that if they aren't hired, then they cannot be held responsible for any problems.
OK - this is all fine - and I don't see anything wrong with it so far.
So the A/E firm uses the report, designs the building, issues it for bid, and it gets built. But the geotech was not given an opportunity to review the plans.
Instead, the contractor is instructed in the specifications to hire a testing lab to "perform tests and inspections" but other than compaction tests, no specific mention is made about reviewing the soil conditions, etc....just compaction tests.
The building ultimately has some severe foundation problems and some of them are possibly due to A/E details not conforming with the original geotech recommendations.
So my basic question is this:
Most construction documents contain drawings and specifications that almost always focus on the requirments of the contractor.
It seems that in this case, and probably in most typical US construction cases, the contract documents don't deal at all with the issue of the geotech reviewing the DESIGN. How many A/E firms do you see giving out their designs back to the geotechnical engineer for review of the design? It seems that it is a common loophole that disallows a good check and quality assurance method....
In this case, the A/E didn't insist on the review, did not follow a certain procedure recommended, and bad things resulted, at least partially from the disconnect between the design and the report.
Also, have you ever seen in any contract documents requirements for the contractor to ask their testing lab to review the design for any problems related to the geotech report that the testing lab may or may not have written?
Thanks for your patience in this long post - and thanks in advance for your replies.
Scenario:
A typical, small building (about 6000 sf) one story, wood framed with brick veneer on concrete spread footings.
An A/E firm hires the geotech via the owner and gets a typical geotechnical report, outlining the soil conditions, bearing pressures, stuff about pavements, etc. Nothing real extraordinary except that the geotech warns about a couple of things:
a) Might be some concerns over the bearing soils - and gives certain recommendations about dealing with those concerns.
b) Says that they (the geotech) should review the plans for conformance with their recommendations.
c) Says that they should be hired to do on-site consulting to verify if the soils are ok, that construction practices are proper, to do testing of compaction, etc.
d) Says that if they aren't hired, then they cannot be held responsible for any problems.
OK - this is all fine - and I don't see anything wrong with it so far.
So the A/E firm uses the report, designs the building, issues it for bid, and it gets built. But the geotech was not given an opportunity to review the plans.
Instead, the contractor is instructed in the specifications to hire a testing lab to "perform tests and inspections" but other than compaction tests, no specific mention is made about reviewing the soil conditions, etc....just compaction tests.
The building ultimately has some severe foundation problems and some of them are possibly due to A/E details not conforming with the original geotech recommendations.
So my basic question is this:
Most construction documents contain drawings and specifications that almost always focus on the requirments of the contractor.
It seems that in this case, and probably in most typical US construction cases, the contract documents don't deal at all with the issue of the geotech reviewing the DESIGN. How many A/E firms do you see giving out their designs back to the geotechnical engineer for review of the design? It seems that it is a common loophole that disallows a good check and quality assurance method....
In this case, the A/E didn't insist on the review, did not follow a certain procedure recommended, and bad things resulted, at least partially from the disconnect between the design and the report.
Also, have you ever seen in any contract documents requirements for the contractor to ask their testing lab to review the design for any problems related to the geotech report that the testing lab may or may not have written?
Thanks for your patience in this long post - and thanks in advance for your replies.