Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Geothermal piping calculations

Status
Not open for further replies.

prichmon

Mechanical
Oct 5, 2010
32
We are looking at replacing a Cooling tower with Geothermal Cooling for a process water loop.

80KW total power usage.
10*F temp differential on cooling tower design
20*F temp design differential on system
operating pressure 30psi

If we move to geothermal cooling our temp differential will be ~35*F+ due to ground water typically not exceeding 60*F. The thought is to simplify the system by elimination of the HX, cooling tower and tanks.

Based on copper pipe of thermal transfer of 13.11 W/M^2*K; PE pipe 7.09 W/m^2*K

1" copper tubing
10*F differential copper equates to ~4595 feet pipe
35*F differential copper equates to ~1315' pipe

Based on data on ground temperature changes the loops need to be ~20' deep to minimize temp swings to the +/-10* range.

I would appreciate if someone with experience in this area could assist me?

Thank you

Rich




 
Replies continue below

Recommended for you

I believe est:
in average N-TX soils there , some dampness, that the horizontal boring would be correlated to 12ft depths (or more if they can get to a stuck drill rod) and near 300ft per ton of to 96f out/ 88 back, in Aug-Sep to the ECL. gle, plastic piping, 20 ft apart runs... ~ 70 gpm, design for UNDER 50ft TDH for some efficient circulation (under 25 psi, all equipment and piping --- ALL in recirculation on the primary ground loop side, if just process cooling)

We have had since 1996 success in 3/4 acre pond , 11 ft deep rack--- coils at 9ft, 70f yielding on a flow of water of 56 gpm a 13 to 14 degree differential
~ 90-out to 87 supplying PROCESS COOLING from 10 coils x 1" PE dr-11; spaced coils (rewound) 6" on center, approx, 5 layers high (16" stacked, approx. 3" apart, like discs on a feeder); 7ft dia finished with 420 ft plus the tails to 5 coils/ea on 2 inch , twice; over:( 360,000 btuh) 30 net cooling tons in the winter, and over 26 tons net cooling in the summer..

2 hp to 3 hp depending on your header lengths and other Td's wanted which shut off 25 hp of refrigeration chillers and all that related maintenance and overhead operating costs.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor