Mbrooke
Electrical
- Nov 12, 2012
- 2,546
Basically I am evaluating a system that requires 6 40/50/60MVA transformers with the 33kv secondaries operated in parallel. Considering the sheer amount of fault current, I plan on using standard 72.5kv (69kv) GIS gear and adapting it as needed, however I am wondering if another option exists like standard 35kv air insulted gear- and if so what the advantages would be.
Also on the same subject... the distribution load will be around 250MVA. I take it that I do not need 4000amp rated bus bars if load is even between each feeder and bus partition?
Open to all and any answer/opinion.
Also on the same subject... the distribution load will be around 250MVA. I take it that I do not need 4000amp rated bus bars if load is even between each feeder and bus partition?
Open to all and any answer/opinion.