thony999
Specifier/Regulator
- Dec 10, 2014
- 14
Happy New Year all!
We recently replaced a section of a 12'' duplex stainless steel natural gas pipeline, which required us replacing a 2m spool and welding two joints.
Because of the length of the line (12km) and the volume of water that will be required, we have decided to treat the 2 welds as golden weld and carry out radiography and ultrasonic tests rather than hydrotesting.
Is there any standard that prevents us from doing this? Is there a mention of situations where we can do this in any of the ISO/API/ASME standards?
Feedback will be appreciated
We recently replaced a section of a 12'' duplex stainless steel natural gas pipeline, which required us replacing a 2m spool and welding two joints.
Because of the length of the line (12km) and the volume of water that will be required, we have decided to treat the 2 welds as golden weld and carry out radiography and ultrasonic tests rather than hydrotesting.
Is there any standard that prevents us from doing this? Is there a mention of situations where we can do this in any of the ISO/API/ASME standards?
Feedback will be appreciated