sjohns4
Civil/Environmental
- Sep 14, 2006
- 123
Our client wants to remove a mechanical bar screen & install a grinder in one of their pump stations. The station has two GR T-10 pumps. The FM exiting the station is 12", the gravity line intering the station is 18". I sales rep I work with quite a bit said he doesnt think a grinder is such a great idea because of the large materials that could come through the 18" line, i.e. bricks. I guess it would be better for a brick to chew up some grinder teeth than a pump impeller though.
Any thoughts? Leave the bar screen, install the grinder, or remove the bar screen with out a grinder?
Thanks,
Mike
Any thoughts? Leave the bar screen, install the grinder, or remove the bar screen with out a grinder?
Thanks,
Mike