CWEng
Materials
- Jul 18, 2015
- 146
We have a new ASME Section VIII job on 1.25CR-.5Mo material where the hardness requirement (weld/HAZ/base metal) is 225 HV10, which is not out of the ordinary for Grade 11 material (at least for B31 pipe with a higher PWHT temperature). However, it is a lower hardness requirement than previous customers where we met their hardness requirements (250 HV10 max) with a 1 hour PWHT at 1275F and 150F preheat on 3/8" thick material. We did meet 225 HV10 with 3 hours at 1275F PWHT on the same material. But our new job requires base/weld metal be qualified for the PWHT cycle needed to build the equipment, the possibility of a repair cycle, plus 3 PWHT cycles left over for the owner. So if we have to qualify 5 PWHT cycles at 3 hours, 15 hours seems to be a bit excessive (for this job with 1.38" wall pipe/fittings).
So I'm looking at options to get hardness lower.
On this job, the customer also requires 300F preheat. Will that be as effective as the additional 2 hours PWHT required on the first job to get hardness down to 225 HV10?
If we do have to do 15 hours PWHT, will that be long enough to start reducing the impact tests values (40 ft-lb average at 0F required per API 934C) or tensile strength of the weld below 75 ksi required for SA-387 Grade 2?
Note we are using GTAW and GMAW with either ER70S-B2L or ER80S-B2
So I'm looking at options to get hardness lower.
On this job, the customer also requires 300F preheat. Will that be as effective as the additional 2 hours PWHT required on the first job to get hardness down to 225 HV10?
If we do have to do 15 hours PWHT, will that be long enough to start reducing the impact tests values (40 ft-lb average at 0F required per API 934C) or tensile strength of the weld below 75 ksi required for SA-387 Grade 2?
Note we are using GTAW and GMAW with either ER70S-B2L or ER80S-B2