voi
Geotechnical
- Jan 29, 2013
- 25
We have a site where up to 5 m the ground is silty clay. We removed the entire clay and reached rock. The building is founded on rock at about 5 m below ground with columns/ pad footings and the walls are supported on strip footings also on the rock. We are near an area with high water table so we have water entering inside the building up to 3 m below ground level. So we are worried that our ground floor slab will be compromised by this water entering the building. If we backfill the entire 5 m excavated area with rocks and concrete and use french drains on the outside will that stop the water entering the building. We have no basement and so the walls below the ground is not reinforced concrete. Our major issue is how to stop water entering the 5 m excavated hole