Galambos
Structural
- Jun 27, 2005
- 231
I have a new slab on metal deck on top of an existing building.
My contractor is requesting to use a grout mix as a pump primer and to leave it in the slab.
The grout mix is of the same compressive strength as my slab on metal deck mix.
To me, this seems REALLY far fetched. Has anyone had a similar request?
My contractor is requesting to use a grout mix as a pump primer and to leave it in the slab.
The grout mix is of the same compressive strength as my slab on metal deck mix.
To me, this seems REALLY far fetched. Has anyone had a similar request?