bridgegrl
Structural
- Jan 31, 2013
- 2
I am working on a project that uses grouted tie-backs in conjunction with a sheet pile retaining wall. The tie-backs are being installed in a material that has been classified as Poorly Graded Sand (Medium Dense) with the boring log showing sand and medium to fine gravel with cobbles and boulders noted. The tie-backs are being installed using a 7" diameter temporary casing. A few of the tie-backs have already been installed and much larger quantities of grout than anticipated were required during the intial grouting before a return was seen at the top of the casing. The worst case was 13 x the area of the casing/hole and the best case was 4 x the area of the casing.
My question consists of two parts:
1) Based on the soil information (before construction began), what would be a reasonable number used to estimate the amount of grout anticipated per hole?
2) Is there a better solution to implement when a much larger amount of grout is required than planned?
Any guidance is appreciated!
My question consists of two parts:
1) Based on the soil information (before construction began), what would be a reasonable number used to estimate the amount of grout anticipated per hole?
2) Is there a better solution to implement when a much larger amount of grout is required than planned?
Any guidance is appreciated!