Hello,
I would like to ask a question about hydrotesting.
We have a fixed tubesheet heat exchanger in our facility and it pass shell hydrostatic test at 9 bar but it fails when we test tubes at 9 bar.
Pressure gage decreases and we observe a leakage shell drain. What is your recommendation? Which point we are missing ?
Best Regards,
I would like to ask a question about hydrotesting.
We have a fixed tubesheet heat exchanger in our facility and it pass shell hydrostatic test at 9 bar but it fails when we test tubes at 9 bar.
Pressure gage decreases and we observe a leakage shell drain. What is your recommendation? Which point we are missing ?
Best Regards,