This is about Auto Centre Project which has some contamination. We removed the 500 gallons waste oil UST (steel) from the ground a few weeks ago. UST was located along the wall outside the building (south side of the building) in front of the second service bay area. Soil samples taken from north wall, east wall and west wall have values above the regulatory guidelines for F4 TPH (C34-C50). North wall is just below the foundation wall and is contaminated. We drilled one bore hole about 6 feet inside the building from the wall and it was okay. Few boreholes about 8 feet from the contaminated walls were also drilled on west, east and south side of the excavation outside the building.
My Questions is
1. How do you remediate the soil below the foundation wall? Some contamination encroaching inside the building too.
2. How do you remove the contaminated soil which is 8 feet deep and 29 feet in length along the wall? Do we need to make 3:1 slope along the foundation wall while removing the soil or building underpinning?
3. Any other alternative or suugestion to remediate the heavy oil contaminated soil below the foundation wall and inside the building close to the wall
I would appreciate if you give me any suggestion how can I deal with it in this situation.
My Questions is
1. How do you remediate the soil below the foundation wall? Some contamination encroaching inside the building too.
2. How do you remove the contaminated soil which is 8 feet deep and 29 feet in length along the wall? Do we need to make 3:1 slope along the foundation wall while removing the soil or building underpinning?
3. Any other alternative or suugestion to remediate the heavy oil contaminated soil below the foundation wall and inside the building close to the wall
I would appreciate if you give me any suggestion how can I deal with it in this situation.